The Master Production Schedule specifies what is produced and when, and is typically derived from the aggregate plan. True or False?

True

The Master Production Schedule is the detailed plan that specifies exactly which finished goods will be produced in each time period. It answers what will be produced and when, turning the broader direction of the aggregate plan into a concrete, time-phased schedule by item. Because the aggregate plan lays out overall demand and capacity, the MPS disaggregates that plan into specific finished-goods quantities for each period, providing the input for production and material planning downstream. It’s focused on manufacturing finished products and their timing, not on partial product sets or services, so the statement is true.

False

It specifies only a portion of products

It is used only for services